QUESTION 1 OF 5 · CommunicationsSingle answer

A project sponsor asks for a status update in the middle of a sprint. Which artifact best communicates overall project health at a glance?

A. The risk register
B. A status dashboard
C. The stakeholder register
D. The work breakdown structure